Norris Lake Water Line Crossing
WHY: To add redundancy with a secondary water line for water supply back-up at the Norris Water Treatment Plant
WHAT: 3,080 linear feet of 24” pipe
WHERE: Norris Lake crossing from Tanglewood Rd, Sharps Chapel to Sugar Camp Ln, Maynardville
WHEN: This project took place on March 15, 2023
HOW MUCH: $7.5 million
Norris Freeway Area Water System Improvements
WHY: To increase capacity in this growing area and replacement of old, deteriorating pipe
WHAT: 24,435 linear feet of pipe ranging in size from 2” to 12″
WHERE: Norris Freeway, Joey Lane, Old Andersonville Pike, Old Jacksboro Pike, Shade Weaver Road, Highland View Road, Shanks Lane, Weaver Cemetery Road, Andersonville Pike, Norris Lane
WHEN: Construction started January 19, 2021. The project estimated completion date is December 2021
HOW MUCH: $1.6 million
Old Downtown Powell Area Water System Improvements
WHY: To enhance reliability to eliminate service outages due to deteriorating pipe
WHAT: 36,462 linear feet of pipe ranging in size from 2” to 12”
WHERE: Ewing Road, Brickyard Road, Spring Street, Harmon Road
WHEN: Construction started February 17, 2020. This project was completed in February 2021.
HOW MUCH: $3.4 million
Broadacres Area Water System Improvements
WHY: To enhance reliability to eliminate service outages due to deteriorating pipe
WHAT: 23,520 linear feet of 6” and 8” pipe
WHERE: Cruze Road, Stamps Lane, and Broadacres Subdivision
WHEN: Construction started August 3, 2020. The project estimated completion date is June 2021
HOW MUCH: $1.5 million
Tell Mynatt/Quarry Road Booster Station
WHY: To address water system pressure issues in this area
WHAT:
WHERE: Tell Mynatt Road
WHEN:
HOW: $300,000
East Copeland Rd & Conner Rd Water System Improvements
WHY: To increase capacity and service reliability – upgrade waterline and combine 3 pump stations
WHAT: 29,900 linear feet of pipe ranging in size from 2” to 12” and 1 – 250 gpm water booster station
WHERE: East Copeland Road and Connor Rd
WHEN: Construction started March 29, 2019. The project was completed in June 2020
HOW MUCH: $2,137,220.43
Pedigo Water System Improvements
WHY: To increase capacity and reliability of water service
WHAT: 10,080 linear feet of 8” pipe
WHERE: Miller Road to Norris Freeway
WHEN: Construction started December 1, 2019. The project was completed in May 2020
HOW MUCH: $687,562.00
Collier Rd Water System Improvements
WHY: To increase capacity and reliability of water service
WHAT: 4600 linear feet of 12” pipe
WHERE: Crown Ridge Lane to West Copeland Drive and Spring Street to Collier Road
WHEN: Construction started April 1, 2019. The project was completed in September 2019.
HOW MUCH: $564,230.05
Bells Campground @ Bull Run Water System Improvements
WHY: To increase capacity and reliability of water service
WHAT: Replace existing 4” pipe with 4,112 linear feet of 8” pipe
WHERE: Bells Campground Rd
WHEN: Construction started June 15, 2017. The project was completed in October 2017.
HOW MUCH: $270,000.00
West Emory @ Cate Road Water and Sewer System Relocation
WHY: To increase capacity and reliability of water service
WHAT: 800 linear feet of 8” pipe
WHERE: West Emory and Cate Road
WHEN: Construction started May 1, 2018. The project was completed in August 2018.
HOW MUCH: $96,704.00
Reed Road & Reed Lane Water System Improvements
WHY: To increase capacity and reliability of water service
WHAT: 7300 linear feet of 6” and 8” pipe
WHERE: Reed Road and Copeland Road
WHEN: Construction started February 1, 2016. The project was completed in March 2016.
HOW MUCH: $235,970.00