Norris Freeway Area Water System Improvements
WHY: To increase capacity in this growing area and replacement of old, deteriorating pipe
WHAT: 24,435 linear feet of pipe ranging in size from 2” to 12″
WHERE: Norris Freeway, Joey Lane, Old Andersonville Pike, Old Jacksboro Pike, Shade Weaver Road, Highland View Road, Shanks Lane, Weaver Cemetery Road, Andersonville Pike, Norris Lane
WHEN: Construction started January 19, 2021. The project estimated completion date is December 2021
HOW MUCH: $1.6 million
Old Downtown Powell Area Water System Improvements
WHY: To enhance reliability to eliminate service outages due to deteriorating pipe
WHAT: 36,462 linear feet of pipe ranging in size from 2” to 12”
WHERE: Ewing Road, Brickyard Road, Spring Street, Harmon Road
WHEN: Construction started February 17, 2020. This project was completed in February 2021.
HOW MUCH: $3.4 million
Broadacres Area Water System Improvements
WHY: To enhance reliability to eliminate service outages due to deteriorating pipe
WHAT: 23,520 linear feet of 6” and 8” pipe
WHERE: Cruze Road, Stamps Lane, and Broadacres Subdivision
WHEN: Construction started August 3, 2020. The project estimated completion date is June 2021
HOW MUCH: $1.5 million
Tell Mynatt/Quarry Road Booster Station
WHY: To address water system pressure issues in this area
WHAT:
WHERE: Tell Mynatt Road
WHEN:
HOW: $300,000